Evaluation plan for year-2 evaluations

Deadline What Responsible
Status
15/8
Agree on top-10 objectives for year-2 evaluations
TB-leads
Started
Missing 1 objective
15/9
Pick scenarios and/or other work to evaluate for each top-10 objective. Assign evaluators for each
TB-leads
 
1/10
All evaluations setup on WIKI. Evaluation-points defined for all evaluations
Evaluators
 
15/11
All evaluations finished
Evaluators
 
15/12
Draft evaluation report (D18.1) ready for review
Bjarne + TB.WP4 members
 

Milestone MS77 (Process for hand-over of evaluation data from testbeds specified) will be discussed in August 2012.