(Delete Red/Amber/Green statuses as applicable)
WP4 - PT.WP.1 Platform Design and Deployment All good!
Progress
- face-to-face meeting in Vienna developers meeting
- coordination of the virtual machine platform release
- discussions on how to include Browser shot tool and its dependencies on the planned virtual machine platform release
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP5 - PT.WP.2 Application Provisioning All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP6 - PT.WP.3 Execution Platform All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP7 - PT.WP.4 Process Management All good!
Progress
- Component plugin for Taverna Workbench supports SPARQL searching for components using the test repository interface
- Taverna Server 2.5a1 almost done (includes built-in support for components)
- Progress on establishing a sane common API for the component repository
- NOTE: Progress will be slow for July; focus will be on talk+poster on Taverna Components for the conference BOSC/ISMB.
Issues, Blockages and Concerns
- What is the status of the parallel/Hadoop compiler? (PT.WP.3)
- How to represent characterisation/QA results in a form consumable by some “SLA assessment component”?
- What language would the SLA be expressed in? (DKF: I think the SLA should not be encoded directly in the workflow as code!)
WP8 - PT.WP.5 Repository Integration All good!
Progress
- We had a WP workshop at AIT with participant form TB and PW where we discussed the integration of preservation workflows. The minutes can be found at: https://portal.ait.ac.at/sites/Scape/PT/Shared%20Documents/Minutes/SCAPE%20Meeting%20Minutes%20PT%20Workshop%20AIT%20Wien.docx
- The implementation of Connector API with Fedora 4 started and the TCK test have been fixed
- Evaluation of Fedora 4 cluster install on SCC cluster as a test setup
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP9 - PC.WP.1 Characterisation Components Be aware! Stopped!
Progress
- Research on Information Extraction is active. An article on a real case digital preservation scenario has been accepted for iPRES.
- We have started planning how best to utilise the new effort from TUW. TUW is going to work with aligning the output from CC tools.
Issues, Blockages and Concerns
- Target tools and tool-types etc for general characterisation will be missing from CP068 (Identification of target tools and tool-types for iteration 03, M29) on account of staffing challenges and sickness. We will try to get a preliminary document ready. The detailed road map will have to be pushed to after the summer vacations. The road map is intended to be complete regarding Information Extraction research and SAZ from MSR.
WP10 - PC.WP.2 Action Services Components All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP11 - PC.WP.3 Quality Assurance Components All good!
Progress
- We had a face-to-face SP meeting in Paris on 18th and 19th June. The minutes and the presentations can be found here
- We started to discuss the integration of TUW effort in QA.
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP12 - PW.WP.1 Automated Watch All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP13 - PW.WP.2 Policy Representation All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP14 - PW.WP.3 Automated Planning All good! Be aware!
Progress
- Prepared draft of SLA specification for continuous monitoring of operations
- Notification API for PLATO - Scout integration: progress, not finished
- Integration of Component Registry - ongoing discussions, see also below
- Implementation of time keeping - rescheduled, to focus on cross topics related to other PW/PC partners
Issues, Blockages and Concerns
- New questions regarding Profiles of QA components may delay implementation, and thus integration in PLATO, this could effect MS62 (due in M32)
- Possible shift of work (implementation of Plan Management API...) could effect MS62 (due in M32), but this will be discussed in the upcoming PW/PT meeting in June
WP15 - TB.WP.1 Web Content Testbed All good!
Progress
- Now starting with the ARC2WARC migration, making good progress
- Tool called CIPEX should help using different identification tools on scale with ARC container files:https://github.com/shsdev/cipex
Issues, Blockages and Concerns
- Reinhard is currently ill, development of ARC2WARC migration tool is stopped
WP16 - TB.WP.2 Large Scale Digital Repository Testbed All good!
Progress
- Have updated/refined the user stories & preparing or starting workflows/testing
Issues, Blockages and Concerns
WP17 - TB.WP.3 Research Datasets Testbed All good! Be aware! Stopped!
Progress
3-4 bullets describing overall progress within WP. Please keep succinct and high-level
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP18 - TB.WP.4 Evaluation of Results All good!
Progress
Work on MS78
- Questionnaire is used for for feedback
- How to evaluate Hadoop-based workflows in TB
Issues, Blockages and Concerns
List any problems, issues or concerns that may be facing this WP.
WP19 - TB.WP.5 Demonstrations All good!
Progress
- Not much activity since creating D19.1
- Partner institutions are aware of what they are expected to demonstrate according to D19.1 and are in the process of preparing the demos.
Issues, Blockages and Concerns
- No issues at the moment.
Next Tasks
- Partners are in the process of preparing Task 2: Coordinate installation of demonstration facilities